Asphalt plant BENNINGHOVEN TBA 200
 

Offer:A-170912-1995-01
Brand:BENNINGHOVEN
Model:TBA 200
Capacity:200 t/h (3% Humidity)
Year of construction:1995

Technical data:

Build by

  • Storage hopper: 1999
  • Automation: 2014
  • 6 dosing hopper of 8-10m3
  • Drum dryer for 200 t/h, liquid gas burner RJ3 FG
  • Filter dust collector BMD Garant 50.000 Nm3 / h
  • Two filler tanks 2x40m3, with filler elevator for filler recovered.
  • Silo of lime 25m3
  • Recycled feeder with elevator for incorporation into the mixer
  • Emulsion tank
  • Liquid Additive System
  • Mixing tower with 5 compartments screen and hot storage of 50 t in 5 compartments
  • 2.5 t mixer
  • Direct Passage
  • Asphalt storage hopper 200 t - 3 compartments Year: 1999

Detailed Description:

Pre-dosing:

  • 4 volumetric pre-dousers / hopper aggregates 8m3
  • 4 extractor mats modular flow rate 150 t / h engine 2,2 kW
  • 2 pre-weight weighers / sand hopper 8 m3 2 weighing mats
  • Variable speed 150 t / h, engine 2,2 kW
  • 1 collector-supply belt flow 200 t / h engine power 7,5 kW

Drying materials:

  • 1 conveyor belt, flow 200 t/h, engine power 4 kW
  • 1 rotary dryer, diameter 2,200 mm, length 9,000 mm, flow 180 t/h at 5% humidity, motor power 4 x 15 kW
  • 1 burner type RAX-JET FG / EG 3
  • Setting range: 1: 6
  • Fan capacity: 21,000 m3 / h
  • Fan motor power: 22 kW
  • Injector flow: 214 - 1.310 kg/h
  • Liquid gas pressure: 10 bar
  • Calorific value: 10.900 kcal/kg (45.600 kJ/kg)

Mixing Tower:

  • 1 hot elevator, flow 200 t/h, engine power 18.5 kW
  • 1 screen 5 cuts, flow 200 t / h with max. in sand 0-2 mm 35% motor 2 x 11 kW
  • Hot storage hopper
  • Number of compartments: 7 total capacity 104 t, specific gravity 1.7 t/m3
  • By-pass compartment 1 13 t
  • Sand compartment 2 38 t
  • Sand compartment 3 11 t
  • Sand compartment 4 11 t
  • Gravelling compartment 5 10 t
  • Gravel compartment 6 11 t
  • Gravelling compartment 7 10 t
  • Filter dust collector BMD Garant 50.000 Nm3/h
  • Weighing aggregates
  • Container capacity 2,500 kg, tolerance / component 5 kg max. 10 kg
  • Weighing filler
  • Container capacity 300 kg, tolerance / component 1 kg max. 2 kg
  • Screw conveyor mixer flow rate 75 t/h, power 5,5 kW
  • Bitumen Weighing
  • Tank capacity 300 kg, tolerance / component 1 kg max. 2 kg
  • Bitumen injection pump, flow 1,140 l/min, engine power 11 kW

Mixer:

  • Capacity 2,500 kg
  • Power 55 kW

Introduction of dop:

  • Tank capacity 400 l, electric heating of the tank 2 x 5,3 kW
  • Volumetric counter 1-24 l/min, pump flow 6 l/min, motor power 0.75 kW
  • Determination 0.3 - 2.5 l / mixed

Filler:

  • Filler, flow 40 t / h, power 5,5 kW
  • Filler silo 1, capacity 50 t, filler transfer screw, flow 40 t, power 11 kW
  • Filler silo 2, 50 t capacity, filler transfer screw, flow 40 t, engine 11 kW
  • Silo buffer, capacity 1,500 kg,
  • Transfer screw: silo-buffer to hot elevator, flow 15 t, motor power 4 kW
    Control panel H AS91 including touch control HAS93.
  • In 1997 there was installed a new 205-tonne asphalt storage hopper in 4 compartments including white hopper.
  • This asphalt Plant is continuously under technical control and with maintenance upgraded and in perfect technical and working conditions.

Status:

Plant ex-work in France.

Sales price 330.000

Condition: Dismantling from 15 to 30 November 2017 - to be agreed 2 weeks before

 

Photos:
 

  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  

Photos
Click on the photo to enlarge it!